Our new plant, Tianjin Minerals Co., Teida, Tianjin is in about 3 kilometers distance of a new terminal, where it is possible to load bulk and break bulk vessels of 70-100.000 mt.

This plant has a total area of 55.000 m².

22.000 m² are used to process bauxite. The first production line is already working and will be added by a second one at the end of second quarter 2014. Therefor the yearly total capacity of the complex amounts to 150.000 tones.

We are working only with the best and most modern equipment. After mining and calcination in our rotary furnace in the Xiaoyi, the bauxite is trucked to the plant in Tianjin, where it is crushed in Barmac crusher to 0-25 mm first and in a second stage to 0-8/10 mm. We work with two Raymon Mills and four Mogensen sieves to finish the product. In the last step we use an additional magnet absorber to remove the final rest of free iron before packing into Big Bag.

The second hall has got about the same size. In this hall we store raw bauxite (0-25/0-50 mm) and Big Bags before transportation to harbor.

Part of this hall includes also the production of proppants.

The offices and our laboratory are in same hall. For quality assurance, including all steps, we have reserved a complete floor.

The gallery shows impressions of the new factory. (date: 01/14)


01ecominerals
02ecominerals
03ecominerals
04ecominerals
05ecominerals
06ecominerals
07ecominerals
08ecominerals
09ecominerals
10ecominerals
11ecominerals
12ecominerals
 
 
Powered by Phoca Gallery

EcoMinerals GmbH
Erkrather Str. 169
40233 Düsseldorf
+49 (0) 211-2338790
This email address is being protected from spambots. You need JavaScript enabled to view it.